Taking just short of 9 months to complete this project, which took a rather dilapidated 6 storey Grade 2 Listed Building to an impressive modern piece of architecture. The installation consisted of:

  • New lighting to each floor for tenants and landlords areas
  • Underfloor power distribution system feeding underfloor fan coil system
  • New High Voltage Packaged Substation craned onto the roof complete with new HV feeder cable fed from basement ring feed units.
  • Three rising busbar systems providing mains distribution power throughout the building.
  • New tenants and landlords mains distribution equipment.
  • Steel Cable Management Systems.